Consumers Energy will be commencing work to rebuild our existing electric line.  The rebuilt line will improve the reliability of electric service in your area and the work will be performed in Consumers Energy’s recorded easement.

The project work area is approximately 1.0 mile and starts at the Northeast corner of the intersection of Grange Hall Road and Fish Lake Road and ends just south of the railroad.  There may be some additional vegetation that will be cleared.

The project schedule is estimated and is weather dependent.

Tree Clearing: As needed

Construction: 12/4/17-2/29/18

Vegetation that will interfere with the rebuilding of the line or may threaten the future reliability of service may be removed.  This work may involve tree clearing, trimming and removal of trees or brush on your property within the existing easement.

If you have any questions, please contact:

Sam Chansler                       Matt Operman

Consumers Energy             Consumers Energy

Forestry Operations             HVD Lines

HVD Line Clearance           Construction

(517) 788-0919                       (989) 513-3283